PROJECT

Project Timeline

Violence in transit has a 24-month duration, starting from June 2011.

In such timeframe, the project foresees a number of actions and five transnational meeting, which will be held twice in Pescara and in Oporto, Barcelona and Rome.

The major steps of the project are scheduled as follows:

MONTHS 2 to 8

  • Research intervention and Partecipant Observation in Pescara (IT), Oporto (PT) and Barcelona (ES) Railway Stations (Work Stream 1)
  • National Desk Researches (IT, PT, ES) on Youth Violence in Transport and Transit Areas

MONTHS 8 to 11

  • Elaboration of 3 Reports on Local Research-intervention
  • Elaboration of 3 National Reports on Youth Violence in Transport and Transit Areas
  • Elaboration of a Transnational Comparative Research

MONTHS 9 to 21

  • Social Interventions Implementation: Outreach Work in the Railway Stations of Pescara, Oporto and Barcelona: participant observation, contact with youth at risk of violence, data collection, counselling, orientation;
  • Social Interventions Implementation: Local Networking, Multiagency and Spatial Approach.

MONTHS 16 to 21

  • Elaboration of Models of Intervention and Models of Transferability through a shared and consultative methodology

MONTHS 21 to 24

  • Editing and Printing of Project Final Report and Guidelines
  • Diffusion of Printed Report and Guidelines
  • Project final conference (Rome)